TESEO AIRLINE SYSTEM CAN BE DRILLED UNDER PRESSURE
To expand a TESEO modular aluminium pipeline system, there is no need to turn off the compressor, shutting down all other work stations and losing all the pressure in the network.
The TESEO magic formula! To open a new air point on an established system under full pressure simply fix the outlet plate where you want it on the pipe run, screw in a ball valve to the outlet plate, screw the special TESEO drilling jig to the ball valve, open the ball valve to allow the drill bit through and drill the aluminium extrusion piping. Swarf is collected in the drilling jig. Remove the drill bit and shut the ball valve, remove the drilling jig, couple up your additional airline or drop column to the ball valve and hey presto, an instant new air point installed in a “live” pipeline without loss of pressure.
For more information contact;
Teseo UK Ltd, Witham, Essex
Tel: 0870 167 2150 Fax: 0870 167 2151
E-mail: sean@teseoair.com Web: www.teseoair.com